Application Process
We strongly recommend that builders or homeowners apply for gas
service installation at the start of the framework on houses under
construction. This enables FHNGA to coordinate our scheduling with
the customers need for service. Another potential problem is that
the builder is responsible for coordinating the scheduling of the
installation of the septic system in relation to the gas service
installation. The builder may avoid these problems by installing
the septic system early or by contacting our Engineering department
promptly before the gas service scheduling.
Generally, FHNGA or its contractor installs the gas service in the
most direct route from the proposed meter location (marked by a
yellow flag at the house) to the gas main at the street. It is the
builder's responsibility to "locate" and mark privately owned
utilities as described on the application.
Please notice that after the initial service installation, any
service requiring height adjustment at the meter location due to
backfilling or other relocation will require additional charges and
further time delays. An order requesting the "relocation of
service" MUST be signed in our office before such work can be
performed.